Schedule
- Phase 1 (1 month duration)
- Project Initiation
- Planning Advisory Committee Meeting 1
- Phase 2 (8 month duration)
- Prepare airport land use compatibility plan
- Inventory
- Base mapping
- Existing land use
- Future land use controls
- Document and policy review
- Identify airport Influence areas
- Identify safety zones
- Identify noise zones
- Identify airspace and overflight zones
- Identify policies
- Administrative Draft airport Land Use Compatibility Plan Update
- Planning Advisory Committee Meeting 2
- Public Workshop 1
- Prepare airport land use compatibility plan
- Phase 3 (7 month duration)
- Public Draft Airport Land use Compatibility Plan Update
- Planning Advisory Committee Meeting 3
- Public Workshop 2
- Environmental Documentation
- Draft final ALUCP
- Displacement analysis
- Administrative draft initial ALUCP
- staff review
- Initial study
- Public review
- Planning Advisory Committee Meeting 4
- Airport Land Use Commission Public Hearing
- Final Airport Land Use Compatibilty Plan Update